ST/CE Civil Engineering LHC Project


 

 

Photos Site de Meyrin Underground of Civil Engineering

 

Status Progress


 

Working face
January 14, 2000
Excavator and working face
January 14, 2000
TI2 excavation
July 17, 2000
TI2 excavation
July 17, 2000
New Coal-cutting machine
August 24, 2000
New Coal-cutting machine
August 24, 2000
TI2 Excavation
September 18, 2000
TI2 Excavation
September 18, 2000
TI2 Excavation
December 09, 2000
TI2 Excavation
December 09, 2000
TI2 Excavation
April 17, 2001
Drainage planket
April 17, 2001
TI2 Concreting
April 20, 2001
TI2 direction SPS
June 29, 2001
UJ22
August 17, 20014
Junction UJ22-TI2
August 17, 2001
TI2 formwork
August 17, 2001
TI2 Tunnel
October 19, 2001
Junction UJ22-TI2
October 19, 2001
TI2 Tunnel
October 19, 2001
Concreting under way
February 21, 2002