CERN/ST-DI/SP (2001-128) | 20 July 2001 |
Presents | : |
J.L. Baldy, M. Bätz, C. Bertone, P. Ciriani, G. Cumer, C.
Colloca, J. Inigo-Golfin, G. Kowalik, J. Kuhnl-Kinel, P. Ninin, R. Nunes, J. Pedersen, R.
Principe, S. Prodon, A. Scaramelli, M. Wilhelmsson / ST D. Gueugnon / PS P. Collier / SL |
Invited | : |
M. Battistin, S. Campbell, G. Lion, H. Nissen / ST |
Excused | : |
I. Bejar Alonso, E. Cennini, P. Chevret, K.
Foraz, C. Jacot, R. Martini, M. Nonis, B. Pirollet, J. Roche, I. Ruehl, E.
Sanchez-Corral, L. Scibile, T. Watson / ST |
The minutes of the last meeting were approved.
The SPS smoke extraction tests have been organized and gave a mixed result. The three
extraction units worked perfectly but pulsing was only available at a single speed,
corresponding to the minimum boundary conditions.
According to the measurements performed during this test, it was suggested to try
calibrating the pulsing speeds in points 2, 4 and 6 with the objective to cope with the
available power supply. In case of this approach would fail, a table of the power needed
will be transmitted to the EL group for action.
As the control part of this project is now under control, a new project leader was appointed during the meeting: M. Nonis. He is in charge of the whole project.
H. Nissen presented the main events that have affected the accelerators between 2/05/2001 and 01/07/2001:
This problem was due to a flood detector in the target area and stopped the TOF experiment. The faulty element has been replaced and the problem is now solved.
The fault occurred on a transformer in SHM18 but was not detected. It caused a defect
on the main 66 kV transformer in the BE substation and as a result 7 power cuts were
generated, which affecting a lot of equipment of the Meyrin site between 10:00 and 15:00.
J. Pedersen explained that this incident was in fact caused by a breakdown of a set of
cable ceiling end and some selectivity problems on the 66 kV network. The 7 power cuts
corresponded to the 7 tries to find a supply source. He noticed that only the PS
accelerator was affected by this problem.
Finally the selectivity problem on the 66 kV network has demonstrated the need of training
of the TCR operators. This will be performed in the next few weeks.
The cooling station 378 was stopped because of a water leak default and affected the TOF cooling station. It took a very long time to try locating the leak. In addition, this operation failed and the refilling of the entire circuit was extremely long. Later on, the fault was identified on a safety valve in building 378.
Some work in BE9 caused a cut of the 48 V network, which stopped the LEP, the SPS and the North Area. H. Nissen pointed out that it took a long time to get access to the BAs and reset the alarms. Indeed, all the BAs were locked.
A network problem occurred in a hub that controlled many data, among themselves the equipments' alarms. This problem caused a disconnection of all the TOF equipment that were passing through this hub.
A water leak occurred in the tunnel. R. Principe explained that Gematec stand-by duty
reacted quite fast but they wer first blocked by an access problem to the tunnel. They
encountered then some difficulties in restarting the installation despite the fact that
they have been trained on this system. ST-CV will send a note to Gematec at this
subject.
This problem also demonstrated the need of a radio piquet to manage the entry into the
tunnel.
The fault was produced in BE9 and has disturbed the cooling tests of the SPS.
The TCR received a call from SM18 indicating that the water was too hot and the equipment rising in temperature. M.C. Morodo Testa and D. Blanc intervened and solved the problem by restarting the fuzzy logic of the variator.
The default was caused by a communication problem between SIG and ST/CV automates,
which disturbed the delta P. As a result, SIG was not able to control water pressure and
asked for a stable consumption without any increase of power.
M. Wilhelmsson explained these first difficulties by the change of range in the CV
network.
The SPS compensator disconnected at the maximum intensity. TCR was informed on this problem by the PCR. The compensator was indeed not fully supervised by the ENS system at that time. It should be operational this week.
This failure highlighted two technical aspects:
The breakdown itself was in fact due to an internal isolation fault on one of the two reactances, a very old equipment, which confirmed ST-EL worries. J. Pedersen recalled that the third reactance, now used as a spare, will be needed in the future for the injection tunnel.
During the last period, the TDS system was not very stable due to the recent increase
of the load. A cleaning of the signal is really needed, as well as a redefinition of all
the values. This represents a really heavy job.
Nevertheless the problem should be solved rapidly as no alarms get through during the
breakdown.
It appeared this morning that the temperature of the main magnet circuit was higher than 40 °C. At the time of the meeting, ST-CV group was still investigating on the problem.
The PS is now on operation and delivering a beam to the SPS, AD and Isolde. The technical stop on 6/6 ran very well.
The only problem to be noticed was an access control default on a door between the MCR and AD experiment. The result of this default was a continuous sound in the control room during the entire week-end. G. Kowalik explained that the problem was due to a breakdown of the GG4 software associated to the door.
D. Gueugnon announced that nTOF experiment has been stopped for two weeks.
He also congratulated J. Kuhnl-Kinel for his coordination work in the PS area.
During this last shut-down an incredible amount of work has been performed. The result is positive: within 2 hours of starting, circulating beam was established.
P. Collier detailed the main activities performed during the last shut-down:
A lot of things ran very well:
On the other hand some points still need to be improved:
In addition, P. Collier mentioned some other difficulties that occurred:
He concluded that the schedule has been maintained despite the limited resources. An overall planning of all the activities is really needed. Big improvement in the communication between ST and SL should also be noticed.
The discussion concentred then on the control of work. It clearly appeared that too few
ST people were present on the work site. Some training should be organised for the new
generation.
J. Pedersen pointed out that ST division should rather supervise companies more than
works. Due to a lack of resources, groups often have to choose between a full worksite
control and a high level project follow-up.
But problems on the work site occur every day (cohabitation between activities, protection
of equipment, safety, etc.) and somebody is really needed on the site to solve all these
problems and to make sure that the firm is doing his job completely.
Coordination of activities on the worksite should also be dealt locally.
On the machine side, 3 technicians spent between 1 and 3 hours a day on the site
controlling work progress.
A. Scaramelli stated that ST division has to revise its organisation in order to
dedicate more resources to the worksite supervision. In addition all the result oriented
contracts have been adjudicated to the lowest bidder. ST division can't escape from
controlling them in order to keep the contracts in hand.
As part of this analysis, the SL file will be useful to understand where the problems are
located and find a good way of communication with SL. It has been agreed with S. Myers to
analyse clear facts.
Concerning the value for money, one of the CERN duties consists of checking that the work has been properly done by the contractor and to activate the according process of payment.
The electrical operation team is made up of 7 people in charge of the on-site work. A
training period will be necessary during the first weeks. The training will be given by
the ST-EL operation team (4 staff members and 3 industrial support personnel).
In addition, until the end of the year, a CERN staff member will systematically accompany
the contactor's personnel on all the stand-by interventions.
S. Campbell precised that only ST-CV alarms are concerned.
He first listed the installations connected with a synoptic, mainly:
Building | Name |
2007, 2001, 2004 | LPI sections (the name "LPI" will be changed to "CTF3") |
274 | West Area |
234 | Lear |
355 | Centre Anneau, East Area, Lear Sud |
237 | Booster |
Some other installations are still connected but without synoptic:
Building | Name |
197 | Isolde: it will be completely connected after the next CAS update |
193 | AD |
358 | Thyristor, Production |
378 | Grouped CV equipment alarm |
141 | Production |
In addition, some installations are simply not connected:
Building | Name |
168 | Test circuits (local installation) |
174 | Experiment (local installation) |
152 | Tekelec (local installation) |
195 | Experiment (local installation) |
118 | Production ED |
180 | Atlas (local installation) |
TT2 | TOF installation |
One known problem concerns the loss of API215 data after the power cut that occurred on 7th June. As the station was restarted before the previous data could have been inserted, the pumping station needed to be stopped in order to correctly install these data. This means that the machine also had to be stopped during this operation.
To solve some of these inconsistencies ST-CV group has launched the COSPCU project, which includes demineralised stations of West Area, main magnet, SW18, chilled water stations 355 and 513. It has to be noticed that building 378 and TOF installation are not part of this project.
S. Campbell gave more information on the installations in building 378. It is possible
for the TCR to rearm a fault without reseting the equipment. But as the operators don't
get any information on the state of the equipment before the fault, it is very difficult
for them to know exactly what to do.
R. Principe explained that a failure in the demineralised water production does not affect
any machine. It gives ST-CV some time to intervene. But he recognised that it is not ideal
to have a single alarm in this building. But the procedure is clear : to call the Gematec
stand-by duty.
In the next future, all the installations should be connected. This represents a very heavy job for the TCR, to be done in collaboration with ST-CV. The deadline is fixed to Easter 2002.
This subject will be presented during the next STTC meeting.
M. Wilhelmsson explained that ST-CV is preparing a whole project for the West Area. He introduced G. Lion who will develop the technical part and M. Battistin in charge of the budget.
G. Lion first presented the elements making up the building 378's installations:
The old cooling towers need to be suppressed. It has been first envisaged to use the
cooling towers located in building 274. This implied to connect the two buildings through
the technical galleries. G. Lion presented some photos of the technical galleries showing
that there is no really space for these pipes and that permanent changes from side to side
are necessary. He announced a cost estimate of 550 KCHF for such a project.
He suggested rather to refurbish the existing 10 MW cooling tower (fan and pump to
rebuild, pipes to install).
A study of the hydraulic circuit gave an estimate of 50 KFF to dismantle the old connection. The power needed in the area represents only 4 MW.
Three groups were used to cool the ISR area. They contain freon R-12 that need to be eliminated by a licensed company. The cost of such a project varies according to the elimination channel:
G. Lion suggested to install demineralised cavities under these three groups. The floor in the basement can support the weight of the cavities.
Globally, demineralised water installations are well maintained but the valves do not comply anymore with the NF standard. The complete change of these valves is estimated to 80 KFF. G. Lion recalled that this installation provides water for the SPS and central heating stations.
A huge maintenance on the installations is really necessary. Present needs should be considered for future projects.
This project is divided into three parts:
The water chillers comprise two groups of 1 MW each. The main users are electrical tests in building 377 and TOF project. Their needs are estimated to about 4 MW. This value should remain stable in the future.
Some parts of the installation need to be renewed :
The new project consists of :
It is estimated to 1,6 MCHF. This part of the project should be discussed with LHC to confirm the needs.
J. Pedersen precised that 1 MW of electrical power will be needed. This implies the installation of one transformer and one switchboard.
9.2.2. Demineralised water
The installation is in a good state. The only interventions to be performed will concern :
This part concerns more maintenance and will be taken from the operation budget.
Two operations are planned:
The estimate arounds 500 KCHF.
R.A.S.
Prochaine réunion le 10 septembre à 15 h |
S. Prodon
Back to STTC Meetings Home page
For
comments and changes send e-mail to ST Secretary
or Divisional
Web masters
Copyright CERN , modified 21/08/2001