Another open question is the CSAM contractor's responsibility in case of (network) problems.
General recommendations that have been written in 20.11.1998 have been distributed and will be discussed by the Safety Alarm System Supervisory Board members internally. They will give a statement for discussion in the next meeting. Nevertheless all participants are invited to give their comments to the board members.
The document is not yet approved officially and is still open for comments. The document is available in EDMS with the document number 346512.
A dedicated meeting with a representative from the Safety Alarm System Supervisory Board, IT/CS and ST/MA will be scheduled to clarify the open questions.
CSAM status report
Luigi Scibile presented the status changes that have happened since the last supervisory board. The detailed specification has been completed by the contractor and the Human Machine Interface proposal validated by the fire brigade, TIS and the TCR.
SCADA evaluation: the performance and reliability tests with PVSS have not been successful and thus the CSAM contractor was forced to start an evaluation for acceptable SCADA products that fulfil the requirements. The requirements have been sent to six product manufacturers. Two products are in the final selection after the performance and reliability tests have been completed. Currently the comparison evaluation is underway and results will be completed by mid-July.
The CSAM planning was realigned to the updated LHC planning in order to optimise costs and the spending profile of the project. The pilot installation is foreseen for Feb/March 2003. It will run "in the background" until June 2003 when the reception test will be done. If the acceptance is successful the CSAM system will become operational in the SCR and TCR. All CERN safety zones will be integrated completely in CSAM when the system will become operational. Thus it is not foreseen to have two parallel systems for the fire brigade.
SCADA performance tests
The status report was covered by the CSAM status report. However, the Board discussed at length and expressed its unhappiness with the apparently unavoidable conclusion that the CERN standard SCADA cannot be used. K. Potter said he would like to know the opinion of JCOP and proposed to invite the JCOP chairman to a future meeting. H. Schonbacher rejected this suggestion on the grounds that it would only confuse further an already very difficult situation and as long as the chosen SCADA is fully compatible with other CERN systems there would be no problem for CSAM. It was confirmed that complete compatibility with standard CERN systems would be fully taken into account.
Consequences on budget cuts
Currently both proposals for the "new" technical network are not funded. An action plan to get a decision on how the necessary money will be found is not yet established. The CSAM project asked also for a dedicated network that has a very simple architecture and will be used for safety data exclusively. This request has not been considered until now due to financial aspects.
A.O.B.
created at Mon Jul 29 12:09:19 METDST 2002 with the
ST/MO/IN - Minutes Maker